Fencing and floodlighting along Indo-Bangladesh

The progress of fencing and floodlighting and the expenditure incurred under various projects along Indo-Bangladesh border as on date is given below:-

Work

Project

Approved length (in km)

Physical progress (in km)

Expenditure incurred (Rs. in crore)

Fence

Phase I

857.37

854.35

1059.00

Phase II

2579.22

1880.77

3155.00

Total

3436.59

2735.12

4214.00*

Replacement of fencing

Phase III

861.00

750.00

695.00

Floodlighting

3117.00

877.00

361.00

*Inclusive of expenditure incurred on construction of roads